Very giant development incurring visitors management points? - Forth Ports’ transport advisors have rechecked a site visitors assessment and confirmed street capacity is on the market. There has additionally been an audit by CEC. The AMC application (present stage) is about design detail. Inside that, design priorities are strolling and cycling by way of segregated routes, together with access to high school, shops, and the medical centre. There have been optimistic discussions with Lothian Buses about extending their community into the location, which has been designed to accommodate such public transport. There'll also be the tram. (These will also benefit present residents.)- The developers will also consider traffic indicators on the entry to site from Sandpiper Drive.



Environmental implications - The outline PPP software was submitted with an environmental impression assessment (EIA). That thought of air quality, ecology and noise. There' seo service -quality measurement.- The PPP application and EIA are 15 years old, however FP also commissioned a phase 1 habitat survey in 2018. This reported no constraints. Additional applications will look at air quality and noise, and can contain engagement with SEPA, SNH and so forth.



Who will fund building of Park? Funding - Scottish Government? - The park might be funded from the identical funds as the overall improvement. So funding will be secured for all of the development, together with the park.- The park, which might be public, shall be maintained after construction by a maintenance company. - This can be funded from the event, i.e. from all homes together with Western Harbour, Components and Platinum Level as a consequence of an current deed of situation.- This shall be separate to the present factoring charges.




All mid-market rental, inexpensive housing not included - not essential? - The present AMC software for 938 units is a part of the prevailing consented grasp-plan. All vital affordable housing has already been delivered. All of this growth shall be mid-market rent (MMR).- There are no plans to include brief-keep commercial customer accommodation or serviced apartments.Slide 20 reveals the 938 units of part 1, while slide 21 provides the waterfront development.



Disabled and elderly services? - The architect confirmed that it will be significant that the event is accessible to all. Building rules and other legislation require varied provisions. An example is level access to all buildings from streets. All flats might be accessible by way of the ground or lifts (or stairs in case of fire). There might be accessible parking spaces and many others, in step with CEC steering.



Waterfront area not included in this software - what will starting date be? - The present software is for 938 homes, then [a part of] the park.- There is no fastened starting date for different phases. Options are being fastidiously considered to establish phase 2’s viability. A Scottish Authorities mortgage is required to trigger further functions because they involve significant spend.



Phasing - northern section of Park final and being used for site autos and equipment for Phase 1 and Section 2 of site. Design Access Statement four (19/00986/AMC) Phasing: Situation four web page 70.



- Development of the development will begin within the south, and journey north. Engineering works are wanted on the waterfront. Mounds of soil there shall be moved back into park space to permit the park’s completion. Completion of the park will occur if/when it is obvious that waterfront is not going to go ahead to growth [if part 2 isn't completed].- The park cannot be finished to the levels planned with out ending part 2. Nevertheless a park of some form may be delivered when section 1 finished.- Phase 2 can proceed as soon because the Scottish Authorities has completed due diligence.- Landscaping issues inside the appliance documentation are about landscaping within section 1.